Transit opens first; streets close and homes are built after.
Every number in the plan says what kind of evidence it rests on. Numbers marked 'Assumption, not data' are invented and have no source.
Transit line paths are drawn straight between stations (approximate).
Extra homes by 2068
Sources: /lesscars design spec
Transit projects at once 4 at once
Sources: SFMTA, Central Subway Project.; Wikipedia, "Van Ness Bus Rapid Transit".; SFMTA, Geary Rapid Project.; SFMTA, L Taraval Improvement Project.
Street projects at once 7 at once Invented
Garage projects at once 2 at once Invented
Housing projects at once 15 at once
Sources: SF Housing Simulator dataset 2026-10-29-14e0eccb: transit.json, parcels/*.json, scenarios/fzp/projects.json, scenarios/fzp/calibration.json.
Duration 108 months
Sources: SFCTA, Geary/19th Ave Subway and Regional Connections Study Strategic Case, Final Report, June 2026.; SFMTA, Central Subway Project.; Tunneling Online, "Worth the Wait" (Central Subway, November 2013).
Peak trips per hour 24 an hour
Sources: SFCTA, Geary/19th Ave Subway and Regional Connections Study Strategic Case, Final Report, June 2026.
Duration 60 months Invented
Sources: SFMTA, Central Subway Extension.
Peak trips per hour 6 an hour
Duration 96 months
Duration 36 months
Sources: SFMTA, Geary Rapid Project.; Wikipedia, "Van Ness Bus Rapid Transit".
Peak trips per hour 11 an hour
Duration 24 months
Sources: SFMTA, L Taraval Improvement Project.
Peak trips per hour 10 an hour Invented
Peak trips per hour 7 an hour Invented
Peak trips per hour 8 an hour Invented
Spaces 1,700 spaces Invented
Sources: DataSF Streets – Active and Retired (3psu-pn9h).
Spaces 300 spaces Invented
Duration 18 months Invented
Duration 12 months Invented
Sources: SFMTA, "Car-Free Market Street starts January 29" (31 December 2019).
Duration 30 months
Sources: SF Board of Supervisors, Resolution 94-13 (Central Freeway freeway agreement).
Right-of-way half-width 11 m Invented
Build duration 30 months
Sources: FHWA, "Rochester, NY: Freeway to Boulevard" project profile.; CBS San Francisco (Phil Matier), "San Francisco's $50 Million Plan To Fill Geary Blvd. Underpass", 7 February 2014.
Right-of-way half-width 10 m Invented
Duration 6 months Invented