Housing policy simulation

Loading the simulation…

Loading map…

Where these numbers come from

How to read this

Every number the simulation uses comes from the best evidence available, and says which kind it is.

Kinds of evidence
TierKind of evidence
0San Francisco project records
1Official published totals
2Inferred from San Francisco records
3Research or literature, not SF records
4Assumption, not data

How projects move through the stages

Discretionary review (Planning Commission or similar): Pre-application

Inferred from San Francisco records

SF Planning records 2015–2026, pooled across pathways (tier 2)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted

based on 211 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 92% advanced, 0% withdrawn
  • Within 24 months: 99% advanced, 0% withdrawn
  • Within 60 months: 100% advanced, 0% withdrawn

Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)

Discretionary review (Planning Commission or similar): In Planning review

San Francisco project records

SF Planning records 2015–2026, discretionary (tier 0)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; discretionary spells since 2015-01-01: n = 921, events = 845; 7 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 52 entries, not asserted

based on 921 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 20% advanced, 1% withdrawn, 0% disapproved, 0% cancelled
  • Within 24 months: 49% advanced, 2% withdrawn, 0% disapproved, 1% cancelled
  • Within 60 months: 82% advanced, 5% withdrawn, 0% disapproved, 1% cancelled

Inferred from San Francisco records Extrapolation beyond month 138 of the table (tier 2)

Discretionary review (Planning Commission or similar): Approved, building permit not yet filed

San Francisco project records

SF Planning records 2015–2026, discretionary (tier 0)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; discretionary spells since 2015-01-01: n = 797, events = 716; 7 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 43 entries, not asserted

based on 797 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 91% advanced, 0% disapproved, 0% cancelled, 0% permit expired
  • Within 24 months: 93% advanced, 0% disapproved, 0% cancelled, 0% permit expired
  • Within 60 months: 95% advanced, 0% disapproved, 0% cancelled, 1% permit expired

Inferred from San Francisco records Extrapolation beyond month 97 of the table (tier 2)

Discretionary review (Planning Commission or similar): Building permit review

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=1.078, withdrawn θ=0.5825, disapproved θ=1.003, cancelled θ=0.8801; pooled spells n = 1748, events = 1510; discretionary spells since 2015-01-01: n = 765; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted

based on 1,748 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 52% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
  • Within 24 months: 71% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
  • Within 60 months: 83% advanced, 2% withdrawn, 0% disapproved, 3% cancelled

Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)

Discretionary review (Planning Commission or similar): Permit issued, not started

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=0.788, withdrawn θ=0.8945, cancelled θ=1.122, expired θ=1.311; pooled spells n = 1224, events = 1117; discretionary spells since 2015-01-01: n = 566; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=10, A=437, w=1.023 for discretionary since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted

based on 1,224 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 66% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 78% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
  • Within 60 months: 85% advanced, 0% withdrawn, 2% cancelled, 8% permit expired

Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)

Discretionary review (Planning Commission or similar): Under construction

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=0.9044, withdrawn θ=1.271, cancelled θ=1.689, expired θ=1.005; pooled spells n = 1274, events = 1204; discretionary spells since 2015-01-01: n = 514; scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=10, A=397, w=1.025 for discretionary since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted

based on 1,274 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 13% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 47% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
  • Within 60 months: 85% advanced, 1% withdrawn, 1% cancelled, 8% permit expired

Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): Pre-application

Inferred from San Francisco records

SF Planning records 2015–2026, pooled across pathways (tier 2)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted

based on 211 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 92% advanced, 0% withdrawn
  • Within 24 months: 99% advanced, 0% withdrawn
  • Within 60 months: 100% advanced, 0% withdrawn

Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): In Planning review

San Francisco project records

SF Planning records 2015–2026, streamlined (tier 0)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; streamlined spells since 2015-01-01: n = 86, events = 69; 3 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 52 entries, not asserted

based on 86 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 71% advanced, 4% withdrawn, 2% cancelled
  • Within 24 months: 86% advanced, 6% withdrawn, 2% cancelled
  • Within 60 months: 91% advanced, 6% withdrawn, 2% cancelled

Inferred from San Francisco records Extrapolation beyond month 8 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): Approved, building permit not yet filed

Inferred from San Francisco records

SF Planning records 2015–2026, pooled across pathways (tier 2)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every entitled spell since 2015-01-01, of any pathway including pathway unknown: n = 868, events = 772; the streamlined cell alone (n = 60, events = 45) is below the thresholds or rejected; 21 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 43 entries, not asserted

based on 868 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 91% advanced, 0% disapproved, 0% cancelled, 0% permit expired
  • Within 24 months: 94% advanced, 0% disapproved, 0% cancelled, 0% permit expired
  • Within 60 months: 96% advanced, 0% disapproved, 0% cancelled, 1% permit expired

Inferred from San Francisco records Extrapolation beyond month 97 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): Building permit review

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1.348, withdrawn θ=1.038, disapproved θ=0.9948, cancelled θ=0.8816; pooled spells n = 1748, events = 1510; streamlined spells since 2015-01-01: n = 45; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted

based on 1,748 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 59% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
  • Within 24 months: 78% advanced, 2% withdrawn, 0% disapproved, 1% cancelled
  • Within 60 months: 88% advanced, 3% withdrawn, 0% disapproved, 2% cancelled

Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): Permit issued, not started

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1, withdrawn θ=1, cancelled θ=1, expired θ=1; pooled spells n = 1224, events = 1117; streamlined spells since 2015-01-01: n = 28; fewer than 30 streamlined spells since 2015-01-01: θ = 1 (pure pooled); permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=0, A=25, w=1 for streamlined since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted

based on 1,224 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 75% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 85% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 60 months: 91% advanced, 0% withdrawn, 1% cancelled, 4% permit expired

Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)

Streamlined approval (state law or the plan's Local Program): Under construction

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1, withdrawn θ=1, cancelled θ=1, expired θ=1; pooled spells n = 1274, events = 1204; streamlined spells since 2015-01-01: n = 25; fewer than 30 streamlined spells since 2015-01-01: θ = 1 (pure pooled); scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=0, A=16, w=1 for streamlined since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted

based on 1,274 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 14% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 51% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
  • Within 60 months: 87% advanced, 0% withdrawn, 0% cancelled, 7% permit expired

Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)

Local Program projects use the streamlined tables

Inferred from San Francisco records

Local Program projects use streamlined-pathway rates (tier 2 proxy)

Local Program = administrative approval, 180-day clock, no DR or appeal (rule, tier 1: Planning Director Bulletin 11); durations and attrition taken from the streamlined tables, n = 253

based on 253 records

records from 2015-01-01 to 2026-10-19

Building permit only: Pre-application

Inferred from San Francisco records

SF Planning records 2015–2026, pooled across pathways (tier 2)

Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted

based on 211 records

records from 2015-01-01 to 2026-10-19

  • Within 12 months: 92% advanced, 0% withdrawn
  • Within 24 months: 99% advanced, 0% withdrawn
  • Within 60 months: 100% advanced, 0% withdrawn

Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)

Building permit only: Building permit review

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=0.8535, withdrawn θ=2.23, disapproved θ=0.9733, cancelled θ=1.731; pooled spells n = 1748, events = 1510; permitOnly spells since 2015-01-01: n = 210; scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted

based on 1,748 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 43% advanced, 3% withdrawn, 0% disapproved, 2% cancelled
  • Within 24 months: 61% advanced, 5% withdrawn, 0% disapproved, 2% cancelled
  • Within 60 months: 72% advanced, 9% withdrawn, 0% disapproved, 7% cancelled

Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)

Building permit only: Permit issued, not started

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=1.237, withdrawn θ=0.9946, cancelled θ=0.9545, expired θ=1.123; pooled spells n = 1224, events = 1117; permitOnly spells since 2015-01-01: n = 127; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=0, A=116, w=1 for permitOnly since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted

based on 1,224 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 82% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 91% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 60 months: 95% advanced, 0% withdrawn, 1% cancelled, 2% permit expired

Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)

Building permit only: Under construction

Inferred from San Francisco records

SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)

Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=1.142, withdrawn θ=1.171, cancelled θ=0.951, expired θ=0.8369; pooled spells n = 1274, events = 1204; permitOnly spells since 2015-01-01: n = 116; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=0, A=110, w=1 for permitOnly since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted

based on 1,274 records

records from 2007-01-01 to 2026-10-19

Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.

  • Within 12 months: 16% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
  • Within 24 months: 56% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
  • Within 60 months: 91% advanced, 0% withdrawn, 0% cancelled, 5% permit expired

Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)

Where new projects start

Chance a parcel starts a project

Inferred from San Francisco records

New-project filing hazard: SF Planning records (2015 on) and new-construction permit filings (2007–2014) on the assessor-roll parcel panel (tier 2)

discrete-time hazard: binomial logit on hostable parcel-months 2007-01 to 2025-12 (one trial per parcel-month), ridge IRLS with RIDGE_LAMBDA = 1 (tier 4) on the bin coefficients, bins merged to at least MIN_BIN_EVENTS = 10 (tier 4) events (binning tier 4); events 720 by first Planning record (2015 on, tier 0 dates) and 551 by first permit filing (before 2015); pre-2015 events detected by first new-construction permit filing (tier 2 proxy); a measurement-definition term (permit-filing proxy vs first Planning record) is fitted and not shipped, so the published level is set by 2015+ first-record events; this is not a market adjustment; basis coefficient = 0.155844; the event is a tier 2 proxy for project initiation (it misses projects that died before filing and dates the rest later); the panel base heights are the tier-3 pre-FZP heights proxy; potentialRatio 0 (the density-capped base envelope yields no units) is a value, not missing: it takes the bottom potentialRatio bin [0, 1) and that bin's fitted hazard; FZP values above the top bin edge take the top bin (clamp): 0.00% of hostable parcels and 0.00% of FZP expected filings have potentialRatio or storiesGap above the panel's at-risk maximum (10513, 80), tier 2, applied beyond historical support (top-bin clamp); permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); the initiation event does not depend on the pathway

based on 1,271 records

records from 2007-01-01 to 2025-12-31

What raises or lowers the monthly chance
FeatureBinCoefficient
Homes allowed ÷ homes there nowunder 1−1.7
Homes allowed ÷ homes there now1 to under 1.51
Homes allowed ÷ homes there now1.5 to under 2−0.62
Homes allowed ÷ homes there now2 to under 30.43
Homes allowed ÷ homes there now3 to under 50.46
Homes allowed ÷ homes there now5 to under 100.31
Homes allowed ÷ homes there now10 to under 200
Homes allowed ÷ homes there now20 or more0.11
Homes there nowunder 10.31
Homes there now1 to under 20.47
Homes there now2 to under 30.01
Homes there now3 to under 5−0.22
Homes there now5 to under 20−0.66
Homes there now20 or more0.1
Lot area (square meters)under 150−0.51
Lot area (square meters)150 to under 250−0.16
Lot area (square meters)250 to under 400−0.06
Lot area (square meters)400 to under 8000.01
Lot area (square meters)800 to under 20000.33
Lot area (square meters)2000 to under 50000.36
Lot area (square meters)5000 or more0.03
Year builtunder 18000.15
Year built1800 to under 19060.29
Year built1906 to under 19300.11
Year built1930 to under 1950−0.44
Year built1950 to under 1979−0.02
Year built1979 or more−0.08
Stories allowed above the existing buildingunder 00.22
Stories allowed above the existing building0 to under 10.16
Stories allowed above the existing building1 to under 2−0.22
Stories allowed above the existing building2 to under 3−0.27
Stories allowed above the existing building3 to under 5−0.23
Stories allowed above the existing building5 to under 10−0.05
Stories allowed above the existing building10 or more0.41
Share of assessed value in the buildingunder 0.11.54
Share of assessed value in the building0.1 to under 0.250.88
Share of assessed value in the building0.25 to under 0.40.2
Share of assessed value in the building0.4 to under 0.55−0.43
Share of assessed value in the building0.55 to under 0.7−1.05
Share of assessed value in the building0.7 or more−1.14
Likely rent-controlled (2 or more homes, built before 1979)no−0.24
Likely rent-controlled (2 or more homes, built before 1979)yes0.24
Land useresidential−1.08
Land usemixed0.49
Land usecommercial0.73
Land usepdr0.87
Land usevacant0.15
Land useother−1.16

How big new projects are

Size of a new project

Inferred from San Francisco records

SF Planning & permit records 2015–2026: new-project size (tier 2)

ratio r = proposed stories ÷ base stories at filing over 797 qualifying histories with a first record in 2015-01-01 to 2026-10-19, snapped to the nearest fill level of the envelope (ties up); r > 1, mostly density-bonus projects, counted as fill 1: 170 of 797 (a model choice, not a data-quality rule); buckets on base stories at filing with edges 4, 6, 8, 12, 999 (tier 4, 999 = any); a bucket with fewer than SIZE_MIN_N = 30 histories merges into its lower neighbour, the first into its upper one; thin buckets merged (12 into the bucket below); probs rounded to 6 decimals, the residual to the largest; base stories at filing is a tier-3 proxy (the current base height, no pre-FZP height map exists)

based on 797 records

records from 2015-01-01 to 2026-10-19

Share of new projects at each fill level
Allowed heightFill levelShare
Up to 4 stories25% of the allowed height2%
Up to 4 stories50% of the allowed height10%
Up to 4 stories75% of the allowed height38%
Up to 4 stories90% of the allowed height0%
Up to 4 stories100% of the allowed height50%
Up to 6 stories25% of the allowed height0%
Up to 6 stories50% of the allowed height9%
Up to 6 stories75% of the allowed height13%
Up to 6 stories90% of the allowed height9%
Up to 6 stories100% of the allowed height70%
Up to 12 stories25% of the allowed height3%
Up to 12 stories50% of the allowed height3%
Up to 12 stories75% of the allowed height16%
Up to 12 stories90% of the allowed height12%
Up to 12 stories100% of the allowed height66%
Up to 999 stories25% of the allowed height17%
Up to 999 stories50% of the allowed height22%
Up to 999 stories75% of the allowed height12%
Up to 999 stories90% of the allowed height5%
Up to 999 stories100% of the allowed height43%

How projects change size

Resizing before construction

Inferred from San Francisco records

SF Planning & permit records 2015–2026: resizing before construction (tier 2)

pairs: permitFiled 621 pairs, own; permitIssued 388 pairs, own; permitFiled compares the PRJ units with the permit's units; permitIssued compares the permit's units with the completed units, completed projects only, and T4c allows no revision on or after construction, so that permit-to-completion change is placed on entering permitIssued (tier 2 attribution); a pair counts when both counts are at least 1 and the later stage was entered in 2015-01-01 to 2026-10-19; a project's first stage is never revised; 134 pairs with a carried-back earlier home count excluded (partner ruling; rule sc.revision.carried-excluded); revised means the counts differ; ratio bins 0.25, 0.5, 0.75, 0.9, 1, 1.1, 1.25, 1.5, 2, 3 (tier 4), a ratio of exactly 3 in the last bin; 14 of 198 revised pairs clamped to 0.25x to 3x (sc.revision.ratio-clamp, tier 4); probs rounded to 6 decimals, the residual to the largest; units are cross-record (T4d)

based on 1,009 records

records from 2015-01-01 to 2026-10-19

Chance of a resize on entering each stage
On enteringChance of a resizeResized smallerResized larger
Building permit review24%56%44%
Permit issued, not started13%84%16%

Which approval path

New projects on Local Program parcels always take the streamlined path. That is a rule (administrative approval with a 180-day clock), tier 1. The shares below apply to other parcels.

Approval path of a new project

San Francisco project records

SF permit & Planning records 2015–2026: pathway of new projects (tier 0)

Pathway shares among 983 qualifying histories with a known pathway whose first record falls in 2015-01-01 to 2026-10-19 (Planning-reliable: the pathway is known only from then); discretionary 687, streamlined 86, permitOnly 210; shares rounded to 6 decimals, the residual to the largest

based on 983 records

records from 2015-01-01 to 2026-10-19

Start at pre-application

San Francisco project records

Share of new projects that start at preApplication (tier 0)

measured after the PPA record series ended (2023-07-07): 177 qualifying filings with a first non-PPA entry in 2023-07-08 to 2026-10-19 (discretionary 104, streamlined 60, permitOnly 13), of which a preApplication entry (discretionary 0, streamlined 0, permitOnly 0); a pathway with no filings has share 0

based on 177 records

records from 2023-07-08 to 2026-10-19

Shares of new projects by approval path
Approval pathShare of new projectsOf those, start at pre-application
Discretionary review (Planning Commission or similar)70%0%
Streamlined approval (state law or the plan's Local Program)9%0%
Building permit only21%0%

How the records were checked