How projects move through the stages
Discretionary review (Planning Commission or similar): Pre-application
Inferred from San Francisco records
SF Planning records 2015–2026, pooled across pathways (tier 2)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted
based on 211 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 92% advanced, 0% withdrawn
- Within 24 months: 99% advanced, 0% withdrawn
- Within 60 months: 100% advanced, 0% withdrawn
Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)
Discretionary review (Planning Commission or similar): In Planning review
San Francisco project records
SF Planning records 2015–2026, discretionary (tier 0)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; discretionary spells since 2015-01-01: n = 921, events = 845; 7 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 52 entries, not asserted
based on 921 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 20% advanced, 1% withdrawn, 0% disapproved, 0% cancelled
- Within 24 months: 49% advanced, 2% withdrawn, 0% disapproved, 1% cancelled
- Within 60 months: 82% advanced, 5% withdrawn, 0% disapproved, 1% cancelled
Inferred from San Francisco records Extrapolation beyond month 138 of the table (tier 2)
Discretionary review (Planning Commission or similar): Approved, building permit not yet filed
San Francisco project records
SF Planning records 2015–2026, discretionary (tier 0)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; discretionary spells since 2015-01-01: n = 797, events = 716; 7 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 43 entries, not asserted
based on 797 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 91% advanced, 0% disapproved, 0% cancelled, 0% permit expired
- Within 24 months: 93% advanced, 0% disapproved, 0% cancelled, 0% permit expired
- Within 60 months: 95% advanced, 0% disapproved, 0% cancelled, 1% permit expired
Inferred from San Francisco records Extrapolation beyond month 97 of the table (tier 2)
Discretionary review (Planning Commission or similar): Building permit review
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=1.078, withdrawn θ=0.5825, disapproved θ=1.003, cancelled θ=0.8801; pooled spells n = 1748, events = 1510; discretionary spells since 2015-01-01: n = 765; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted
based on 1,748 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 52% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
- Within 24 months: 71% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
- Within 60 months: 83% advanced, 2% withdrawn, 0% disapproved, 3% cancelled
Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)
Discretionary review (Planning Commission or similar): Permit issued, not started
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=0.788, withdrawn θ=0.8945, cancelled θ=1.122, expired θ=1.311; pooled spells n = 1224, events = 1117; discretionary spells since 2015-01-01: n = 566; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=10, A=437, w=1.023 for discretionary since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted
based on 1,224 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 66% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 78% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
- Within 60 months: 85% advanced, 0% withdrawn, 2% cancelled, 8% permit expired
Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)
Discretionary review (Planning Commission or similar): Under construction
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to discretionary 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from discretionary spells since 2015-01-01 (proportional hazards): advance θ=0.9044, withdrawn θ=1.271, cancelled θ=1.689, expired θ=1.005; pooled spells n = 1274, events = 1204; discretionary spells since 2015-01-01: n = 514; scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=10, A=397, w=1.025 for discretionary since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted
based on 1,274 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 13% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 47% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
- Within 60 months: 85% advanced, 1% withdrawn, 1% cancelled, 8% permit expired
Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): Pre-application
Inferred from San Francisco records
SF Planning records 2015–2026, pooled across pathways (tier 2)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted
based on 211 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 92% advanced, 0% withdrawn
- Within 24 months: 99% advanced, 0% withdrawn
- Within 60 months: 100% advanced, 0% withdrawn
Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): In Planning review
San Francisco project records
SF Planning records 2015–2026, streamlined (tier 0)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; streamlined spells since 2015-01-01: n = 86, events = 69; 3 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 52 entries, not asserted
based on 86 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 71% advanced, 4% withdrawn, 2% cancelled
- Within 24 months: 86% advanced, 6% withdrawn, 2% cancelled
- Within 60 months: 91% advanced, 6% withdrawn, 2% cancelled
Inferred from San Francisco records Extrapolation beyond month 8 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): Approved, building permit not yet filed
Inferred from San Francisco records
SF Planning records 2015–2026, pooled across pathways (tier 2)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every entitled spell since 2015-01-01, of any pathway including pathway unknown: n = 868, events = 772; the streamlined cell alone (n = 60, events = 45) is below the thresholds or rejected; 21 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 43 entries, not asserted
based on 868 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 91% advanced, 0% disapproved, 0% cancelled, 0% permit expired
- Within 24 months: 94% advanced, 0% disapproved, 0% cancelled, 0% permit expired
- Within 60 months: 96% advanced, 0% disapproved, 0% cancelled, 1% permit expired
Inferred from San Francisco records Extrapolation beyond month 97 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): Building permit review
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1.348, withdrawn θ=1.038, disapproved θ=0.9948, cancelled θ=0.8816; pooled spells n = 1748, events = 1510; streamlined spells since 2015-01-01: n = 45; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted
based on 1,748 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 59% advanced, 1% withdrawn, 0% disapproved, 1% cancelled
- Within 24 months: 78% advanced, 2% withdrawn, 0% disapproved, 1% cancelled
- Within 60 months: 88% advanced, 3% withdrawn, 0% disapproved, 2% cancelled
Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): Permit issued, not started
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1, withdrawn θ=1, cancelled θ=1, expired θ=1; pooled spells n = 1224, events = 1117; streamlined spells since 2015-01-01: n = 28; fewer than 30 streamlined spells since 2015-01-01: θ = 1 (pure pooled); permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=0, A=25, w=1 for streamlined since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted
based on 1,224 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 75% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 85% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 60 months: 91% advanced, 0% withdrawn, 1% cancelled, 4% permit expired
Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)
Streamlined approval (state law or the plan's Local Program): Under construction
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to streamlined 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from streamlined spells since 2015-01-01 (proportional hazards): advance θ=1, withdrawn θ=1, cancelled θ=1, expired θ=1; pooled spells n = 1274, events = 1204; streamlined spells since 2015-01-01: n = 25; fewer than 30 streamlined spells since 2015-01-01: θ = 1 (pure pooled); scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=0, A=16, w=1 for streamlined since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted
based on 1,274 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 14% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 51% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
- Within 60 months: 87% advanced, 0% withdrawn, 0% cancelled, 7% permit expired
Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)
Local Program projects use the streamlined tables
Inferred from San Francisco records
Local Program projects use streamlined-pathway rates (tier 2 proxy)
Local Program = administrative approval, 180-day clock, no DR or appeal (rule, tier 1: Planning Director Bulletin 11); durations and attrition taken from the streamlined tables, n = 253
based on 253 records
records from 2015-01-01 to 2026-10-19
Building permit only: Pre-application
Inferred from San Francisco records
SF Planning records 2015–2026, pooled across pathways (tier 2)
Aalen–Johansen cumulative incidence, right-censored at last observation, left-truncated at window start; pooled across pathways: every preApplication spell since 2015-01-01, of any pathway including pathway unknown: n = 211, events = 211; every preApplication spell is pooled across pathways, because a PPA-only record's pathway is assigned, not observed: n = 211 (calibration.method.ppaPooled); 6 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2023 (to 2023-07-07): 0 entries, not asserted
based on 211 records
records from 2015-01-01 to 2026-10-19
- Within 12 months: 92% advanced, 0% withdrawn
- Within 24 months: 99% advanced, 0% withdrawn
- Within 60 months: 100% advanced, 0% withdrawn
Inferred from San Francisco records Extrapolation beyond month 12 of the table (tier 2)
Building permit only: Building permit review
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=0.8535, withdrawn θ=2.23, disapproved θ=0.9733, cancelled θ=1.731; pooled spells n = 1748, events = 1510; permitOnly spells since 2015-01-01: n = 210; scaled hazards capped at 1 at 1 pooled event durations; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 100 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 39 entries, not asserted
based on 1,748 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 43% advanced, 3% withdrawn, 0% disapproved, 2% cancelled
- Within 24 months: 61% advanced, 5% withdrawn, 0% disapproved, 2% cancelled
- Within 60 months: 72% advanced, 9% withdrawn, 0% disapproved, 7% cancelled
Inferred from San Francisco records Extrapolation beyond month 131 of the table (tier 2)
Building permit only: Permit issued, not started
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=1.237, withdrawn θ=0.9946, cancelled θ=0.9545, expired θ=1.123; pooled spells n = 1224, events = 1117; permitOnly spells since 2015-01-01: n = 127; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1036, w=1.112 pooled; X=0, A=116, w=1 for permitOnly since 2015-01-01; 95 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 27 entries, not asserted
based on 1,224 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 82% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 91% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 60 months: 95% advanced, 0% withdrawn, 1% cancelled, 2% permit expired
Inferred from San Francisco records Extrapolation beyond month 83 of the table (tier 2)
Building permit only: Under construction
Inferred from San Francisco records
SF permit records 2007–2026, pooled across pathways before 2015, scaled to permitOnly 2015–2026 (tier 2)
Pooled Aalen–Johansen over all spells since 2007-01-01, the first assessor roll (existing homes at filing are known only from then; pooled across pathways before 2015; pathway unknowable); cause-specific hazards scaled by θ = (O+5)/(E+5) from permitOnly spells since 2015-01-01 (proportional hazards): advance θ=1.142, withdrawn θ=1.171, cancelled θ=0.951, expired θ=0.8369; pooled spells n = 1274, events = 1204; permitOnly spells since 2015-01-01: n = 116; permit-only histories before 2015 count as pathway unknown: n = 2435 of 2645 (calibration.method.permitOnlyPre2015); 116 completions without a construction start (no FCD) kept in incidence, durations from histories with an FCD (rule sc.stages.no-fcd-duration): X=116, A=1053, w=1.11 pooled; X=0, A=110, w=1 for permitOnly since 2015-01-01; completion = first TCO/CFC, else permit `completed_date`; TCO data start in 2018, so earlier completions are dated later (bias toward longer durations); 115 spells from histories with an imputed stage date (rule sc.stages.gap-impute; bias toward zero-duration spells); partial year 2026 (to 2026-10-19): 20 entries, not asserted
based on 1,274 records
records from 2007-01-01 to 2026-10-19
Building-permit stages use records from 2007 on, the first year the assessor's roll can say how many homes a site had before the project.
- Within 12 months: 16% advanced, 0% withdrawn, 0% cancelled, 0% permit expired
- Within 24 months: 56% advanced, 0% withdrawn, 0% cancelled, 1% permit expired
- Within 60 months: 91% advanced, 0% withdrawn, 0% cancelled, 5% permit expired
Inferred from San Francisco records Extrapolation beyond month 111 of the table (tier 2)